ACTIVITY | COST ESTIMATE(USD) | |
---|---|---|
Short Term Projects | Dining hall finishes | $8800 |
Teachers /staff quarters | $57,900 | |
Lister engine to pump water from steam wells | $1500 | |
Soccer field final touches (side sitting area excavations | $5400 | |
Furniture for the library, computer lab and teaching staff offices | $2,300 | |
Tree and flower planting | $1,800 | |
Middle Term Projects | Construction of workshop Construction classes | |
Carpentry class (structure) | $4800 | |
Electricity class(structure) | $4800 | |
Home science class (structure) | $4800 | |
Backup Generator | $15,000 | |
Accessibility project for walkways around campus | $31,000 | |
Long Term Projects | Campus Concrete block Perimeter Wall | $38,000 |
– | Total Cost | $248,900 |